Knowledge for the Sulphuric Acid Industry
Sulphuric Acid on the Web
Introduction
General
Equipment Suppliers
Contractor
Instrumentation
Industry News
Maintenance
Acid
Traders
Organizations
Fabricators
Conferences
Used
Plants
Intellectual
Propoerty
Acid
Plant Database
Market
Information
Library
Technical Manual
Introduction
General
Definitions
Instrumentation
Plant Safety
Metallurgial
Processes
Metallurgical
Sulphur Burning
Acid Regeneration
Lead Chamber
Technology
Gas Cleaning
Contact
Strong Acid
Acid Storage
Loading/Unloading
Transportation
Sulphur
Systems
Liquid SO2
Boiler Feed Water
Steam Systems
Cooling Water
Effluent Treatment
Utilities
Construction
Maintenance
Inspection
Analytical Procedures
Materials of Construction
Corrosion
Properties
Vendor Data
DKL Engineering, Inc.
Handbook of Sulphuric Acid Manufacturing
Order
Form
Preface
Contents
Feedback
Sulphuric Acid
Decolourization
Order Form
Preface
Table of Contents
Process Engineering Data Sheets - PEDS
Order
Form
Table of Contents
Introduction
Bibliography of Sulphuric Acid Technology
Order Form
Preface
Contents
Acid Plant Database July 16, 2022
Owner | Minera y Metalurgica del Boleo S.A. |
|
Location |
Carretera Transpeninsular No. 1 Km. 5.5 al Norte de Santa Rosalía Santa Rosalía, BCS 23920 Mexico |
|
Background | Company
is controlled by Baja Mining Corporation www.bajamining.com (Link Broken) |
|
Website | www.mmboleo.com | |
Plant | El Boleo | |
Sulphuric Acid | Liquid SO2 | |
Coordinates* | 27° 22' 5" N, 112° 17' 50" W | - |
Type of Plant | Sulphur Burning | |
Gas Source | Sulphur | Sulphur Burning Acid Plant |
Plant Capacity | 2400 MTPD | 300 MTPD |
SA/DA | DA | - |
Status | Operating | Operating |
Year Built | 2014 | 2015 |
Technology | MECS, Inc. | Noram Engineers and Constructors |
Contractor | SNC Lavalin Engineers and Constructors | - |
Remarks | HRS and
Turbogenerator Reported Capital Cost: $120 million |
|
Pictures | ||
General | The Acid Plant and Power Cogeneration (cogen) Plant are both critical path items in the construction schedule. Accordingly, to ensure their timely availability in 2009, the Company has placed the order for a 46 megawatt turbine and generator (TG) set which has been identified as the single longest lead item. The cost of this TG package is approximately US$10 million. Delivery is expected in 18-22 months. The Cogen Plant is an integral part of the acid plant and utilizes heat recovered from the burning of sulphur to generate power. When fully operational, it is anticipated that this facility will provide almost all of the power required for the mine and process plant. In addition, the Company has issued a “Letter of Award and Limited Authorization to Proceed” to SNC-Lavalin Engineers & Constructors Inc. for basic engineering and procurement services for the 2400 tonnes per day acid plant, complete with heat recovery system and the 46 MW turbo generator package. The parties are currently working on concluding a definitive agreement for all services; however work has commenced based on the award. | |
References | - | |
News |
October 9, 2016 - A Vancouver junior miner that developed a $2 billion copper mine in Mexico has been reduced to a penny stock company with dwindling prospects and may now have to walk away from the mine it helped build. Baja Mining Corp. (TSX-V:BAJ) has announced a 1-20 share rollback and a name change. Baja’s share value fell 33%, from $0.015 to $0.01, October 6, following the announcement on October 5. Running at a loss, it cannot afford its share of a recent cash call to continue funding the Minera y Metalúrgica del Boleo mine in Mexico, the company says. The announcement comes after nearly a year of the company’s stock languishing at around $0.01 per share. Founded by Vancouver’s John Greenslade, Baja had partnered with Korean investors to develop the Boleo copper mine in Mexico, but lost control of the project after it was discovered that the mine would cost about $750 million than expected to build. Greenslade staked the property on the Baja California peninsula of Mexico in the 1990s and in 2010 Baja raised $1 billion. Greenslade was forced to resign as CEO after it was discovered that the project’s capital costs had been dramatically underestimated. Baja ended up losing its majority stake in the mine project to a consortium of Korean investors. And now it appears Baja could lose its remaining 10% stake in the mine, which went into production in early 2015, 18 months behind schedule. In its most recent management and discussion analysis, Baja says it has told Minera y Metalúrgica del Boleo – controlled by a consortium of Korean investors – that it won’t be able to cover its 10% of a recent $40 million cash call to continue fund operations. “This may result in a further decrease in Baja’s ownership of the Boleo Project,” the company states. In the first half of 2016, Baja recorded a net loss of $1.6 million, and the company says the Boleo mine has provided no source of income, only losses. With working capital of just $54,000 at the end of the first half of 2016, Baja now appears to be bailing on the Boleo project. The company plans to change its name to Camrova Resources Inc. and plans to consolidate its 340.2 million common shares to 17 million in a 1-20 rollback. January 26, 2015 - Minera y Metalurgica del Boleo (MMB) obtains its first copper production from the process of crushing, leaching, extracting and electrowinning in its mine-metallurgic project “El Boleo”. The company is leaded by a group of Korean companies headed by Korean Resources Corporation (KORES) with a 90% of ownership with Baja Mining retained the 10% of the ownership. MMB is very happy and proud to obtain this first copper production”. “El Boleo” is the effort of hard work for over 4 years; since they received the funding financing in 2010 for starting the construction of the process plant and finished at the end of the last year; in 2012, MMB change its management, the Korean Consortium increasing its participation on the company and by September 2014, Minera y Metalúrgica del Boleo suffers a tragic blow, two Korean Directors died during the hurricane “Odile”; after all this difficulties, they finally achieve the most important milestone of the Company, its first copper. A major highlight of this project was the investment of around of $2.0 billion dollars; which has never occurred for any unitary company, for the creation of a new mining operation in the Baja California Sur state. The annual production capacity of copper is 51,000 tons of copper cathodes with a 99.99% of purity, of metallic cobalt is estimated in 1,700 tons per year and zinc sulphate is around 25,000 tons each twelve months. Due this production volume, “El Boleo” project will place again Santa Rosalia as a mining town, Baja California Sur as the second copper producer at national level and as a first metallic cobalt producer in Mexico. The minimum lifetime of the mine is estimated in 22 years. MMB has already a production estimation for this 2015; it is considered the production of 24,000 tons of copper, 8,000 tons of zinc sulphate and 600 tons of metallic cobalt. “El Boleo” is a water and energy self-sufficient project, since they produce their fresh water through desalinate plants and in the energetic aspect they produce their own energy through motors generators and a steam turbine, so, they will not affect the resources designated for the population. MMB nowadays develop more than 1,000 direct jobs, being the 65% natives of Santa Rosalía. It is important to remark, that MMB has high responsibility levels in the care of the environment and the company have been characterized by develop high standards in the carefulness of our economic, environmental and social surroundings. November 23, 2010 - Baja Mining Corp. ("Baja") is pleased to announce that its Boleo Project is now fully funded for construction following Baja’s recently completed US$858 Million project financing and C$184 Million bought deal financing. “After signing the US$858 Million project financing facilities on September 28, 2010, the final component required to complete this milestone financing was the equity raise of C$184 Million” said John Greenslade, President & CEO, “Today, with over US$1 Billion raised, we are fully funded and ready to move the Boleo Project to the construction phase with the goal of reaching copper production in 2013”. Michael Shaw, Chief Operating Officer, stated, “We are a ‘shovel ready’ project with mass earthworks ready to start within a month. Our most significant long lead equipment has been fabricated or is in an advanced state of fabrication. We have released our EPCM contractor and construction activities are recommencing at site”.
September 29, 2010
- Baja Mining Corp. (“Baja”) is pleased to announce that its 70% owned
project company, Minera y Metalurgica del Boleo S.A. de C.V. (“MMB”), has
finalized and signed US$858 million of financing facilities for the
construction and development of the Boleo project (the “Project”) located in
Baja California Sur, Mexico. The financing facilities comprise US$823
million of project financing facilities (the “Debt Facilities”) and a US$35
million equity cost overrun support facility (the “Equity Cost Overrun
Agreement”). “The closing of
the Boleo debt financing and the cost overrun funding are major milestones
for Baja and for the mining industry in Mexico,” said John Greenslade,
President & CEO. “The closing of these facilities is a testament to the
compelling economics of the project and to the strong effort of our team. It
also means full-scale construction activities at Boleo can commence
imminently.” Tom Ogryzlo, Chair of the Board, stated, “being associated with
the creation of the Boleo project has been one of the most memorable events
of my long career in the mining industry. I am very proud to be working with
such an outstanding management team.”
The US$823 million of Debt Facilities, representing the entire amount of
debt financing required to develop the Project, will be provided to MMB by
the Export-Import Bank of the United States (“EXIM”); Export Development
Canada (“EDC”); the Korea Development Bank (“KDB”); and by a group of
commercial banks comprised of Barclays Capital (the investment banking
division of Barclays Bank PLC), Standard Bank Plc, Standard Chartered Bank,
UniCredit Bank AG and WestLB AG (together, the “Commercial Lenders”). February 3, 2009 -
Following the previously announced slowdown in Project construction the
Company has been devoting significant time to progressing detailed
engineering. Work also continues at Boleo to complete certain infrastructure
on site, such as the phase 1 construction camp and desalination plant. The
Company has also commenced a capital and operating cost review, as it
believes that one positive outcome of the global financial crisis and the
related easing of the construction market, is the potential for a reduction
in capital and operating costs in the near term. The slowing of the original
construction schedule now enables the Company to take advantage of the
reduced cost environment. The re-costing estimate is being undertaken in
Vancouver together with the assistance of Baja's Korean partners. October 29, 2008 - Baja Mining advises that due to the current global financial crisis, it has elected to delay construction activities at the Boleo Project, Mexico. While project economics remain robust even at low metal prices, the impact of the current financial crisis on short term metal prices and hedging prices, coupled with an effective shutdown of the global bank syndication and equity markets, require Baja to revise its constuction schedule. On going baselining and engineering activities at Boleo will continue, as will completion of the Boleo construction camp and certain other on-site infrastructure activities. However, other activities at Boleo will be suspended until market conditions improve. |
MTPD - Metric Tonne per Day
MTPA - Metric Tonne per Annum
SA - Single Absorption
DA - Double Absorption
* Coordinates can be used to locate plant on Google Earth